Operation Manual / TPL69-A10 / -A30 ... TPL77-A10 / -A30
5 Maintenance / 5.4 Cleaning turbine blades and nozzle ring in opera-
tion
© Copyright 2018 . All rights reserved. HZTL2481_EN Revision C May 2018
5.4.1 Wet cleaning turbine and nozzle ring during
operation
Prerequisites for wet cleaning of turbine
The following operating state and prerequisites have been tested and
approved by ABB Turbo Systems for the cleaning process:
u The engine has just been started or the engine load has been reduced
as far as possible (best cleaning is achieved at a load level of roughly
10...15%).
u As soon as the turbine inlet temperature is stable and below 430°C,
wait at least another 10 minutes for the charger parts to cool down.
u Start cleaning cycle according to following description Wet cleaning
procedure.
Page 58 / 136

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB TPL69-A Series and is the answer not in the manual?

ABB TPL69-A Series Specifications

General IconGeneral
BrandABB
ModelTPL69-A Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals