ADCP-61-471 • Issue 4 • June 2000 • Section 2: Operation and Maintenance
2-26
© 2000, ADC Telecommunications, Inc.
NTP-011
Page 2 of 2
Do Items Below in The Order Listed For Details Go To
7. Clear Alarm History. DLP-527
8. Enter Target Identifier and set date and time now or during
provisioning (the turn-up process). DLP-528
9. Configure DS3 MUX as required. DLP-529
10. Configure RLX or RLXIOR modules as required. DLP-534 or DLP-533
11. Check RLX voltage to repeater. DLP-567
12. Connect the test equipment at both ends of the system and perform
an end-to-end test. DLP-522
13. If the DS3 MUX protect module is installed:
Execute Force/APS commands through the Craft Interface. DLP-537
Perform Manual (Force) Switch to Protect test on DS3 MUX
module. DLP-511
Perform APS test on DS3 MUX module. DLP-512
14. At both ends of the circuit, make any necessary cross-connects at
the DSX. DLP-569
15. Log off from the Craft Interface system. DLP-564
16. Complete assignment forms and update office records as required
by local procedures. DLP-523

Table of Contents