4.2.4 Powering with 115 Volts AC∽
Note: Voltage/fusing are factory set. Use a wire gauge appropriate to service
installation.
See Appendix A for Power and Fuse Requirements and Appendix E
Engineering Drawing 613-816, Service Connections.
To connect 115 VAC to Terminal TB1:
• AC Hot to terminal labeled L1/HOT
• AC Neutral to terminal labeled N/NEUT
• AC Ground to Safety Ground stud.
4.2.5 Powering with 220/230 Volts AC∽
Note: Voltage/fusing are factory set. Use a wire gauge appropriate to service
installation.
See Appendix A for Power and Fuse Requirements and Appendix E
Engineering Drawing 613-816, Service Connections.
North American Connection, as follows to TB1:
• AC Hot1 to terminal labeled L1/HOT
• AC Hot2 to terminal labeled N/NEUT
• AC Ground to Safety Ground stud
European Connection, as follows to TB1:
• AC L1 to terminal labeled L1/HOT
• AC N to terminal labeled N/NEUT
• AC Ground to Safety Ground stud
4.2.6 Powering with 24 Volts DC
Note: Voltage/fusing are factory set. Use a wire gauge appropriate to service
installation.
See Appendix A for Power and Fuse Requirements and Appendix E
Engineering Drawing 613-816, Service Connections.
To connect 24VDC to Terminal TB1:
• +24 V DC to terminal labeled 24 V DC
• 24 V Return to terminal labeled RTN