5
4”
16”
CONCRETE PAD PLACEMENT
FOR SL-90DC
24”
24”
15”
18”
RED HEAD BOLTS
FOUR PLACES ½”X 3 ½”
Area for conduit(s)
Operator concrete pad
Operator frame
Operator plastic cover
GATE TRACK GATE
GATE TRACK
FOOTING
GATE TRACK
FOOTING
Minimum 5”
10”
8”
24”
4”
When possible
Install 4” above
Ground
Footing for
Gate operator
½”
10
13
½”
8
1
4
/
Drive chain level for front
mount
Drive chain level for rear
mount
Low voltage single
conduit for Master/Slave
High voltage
conduit
Total cover higth