Checking combustion CO
2
Take the case o the boiler;
Set the boiler on full load (see Step 1)
The CO
2
values are set by using an Allen key (2 mm), or a large flat head screwdriver,
on the screw “B
Please observe the following rotating direction:
Clockwise means less CO
2
Counter clockwise means more CO
2
Step 3: Adjustment on the gas valve
Adjust the gas valve only in case the measured values lie out of the range of the values mentioned in step 1 or 2.
°C
A
B
AFTER THIS SETTING HAS BEEN MADE, ONCE MORE TEST THE CO
2
VALUE
AT FULL LOAD AND LOW LOAD WITH THE CASE ON. SEE STEP 1 AND 2.