Selection of installation
location:
Location for installation of the Unit must be
selected so that the treated water can flow
automatically (see Principal diagram 1).
IMPORTANT! If the Unit is not mounted
on reinforced concrete rings, it may not
be installed on the part of the plot of
land intended for transport traffic and/or
parking, as well as on the part of the land
where storm water or high groundwater
accumulates.
The Unit must be easily accessible for
frequent inspections.
It is necessary to maintain the distance
from adjacent objects established by the
applicable legal regulations.
The Unit and the systems ensuring
its functionality must be installed in
accordance with the requirements of the
effective legal regulations, the technical
or work project of the building, instruc-
tions for installation work and these
recommendations.
Preparation for
construction:
The wastewater pipe from the source to
the Unit must be laid with a slope suitable
for gravity flow of wastewater.
IMPORTANT! Burying the pipe for the
discharge of wastewater to the Unit may
not exceed 1 m from the ground surface,
which must be taken into account in
advance in the formation of the terrain.
For pipes buried 1 m and more, the
sewage lifting pump station must be
installed upstream of the Unit.
The diameters of the wastewater
effluent and treated water pipes MUST
correspond to the diameter of the built-in
couplings in the Unit.
The depth of the wastewater pipe must
match the depth of the Unit coupling.
The pit for the convenient installation
of the Unit must be at least 150 cm
wider than the diameter of the Unit. The
installation site should be cleaned of
debris and be free of vegetation (trees),
the roots of which may interfere with the
installation and subsequent operation of
the Unit.
1.1
1.3
1.2
1.
2.1
2.4
2.3
2.2
2.