Start-up Procedure
-72-
Verify Inlet Shut-off Valve Operation (if installed)
Step 11: If the Inlet Shut-off Valve is installed, the valve will open during the Start-up Sequence. Verify
that the valve is open by drawing water from a faucet (specifically hot water). This is shown in Figure 111.
Program the Setback Control (if installed)
Step 12: Refer to the instructions included with the Setback Control on how to program the control.
The Start-up Procedure is complete. The installation of the Accessory
Module and its components is complete.