BRUNSWICK INSTALLATION MANUAL PAGE 13
EDINBURGH
RAIL & APRON ASSEMBLY
FIGURES ONE
Step #1: Position (2) side rails, (1) head rail and (1) foot rail
upside down in their respective positions on a protected surface.
Step #2: Insert (4) 5/16-18UNC X 4 Threaded Rods into each
side rail end. Slide the rails into position aligned with the
threaded end rod. Using (8) Flat Washers, (8) 5/16 Ext. Tooth
Lock Washers and (8) 5/16-18UNC Hex Nuts align and draw
together each of the four connections and tighten each securely.
FIGURE ONE
FIGURE TWO
Step #3: Thread (18) 3/8-16UNC X 2-3/4 Threaded Rods
into each of the eighteen locations in the bottom of all four
rails. For best results, turn each Threaded Rod all the way
in until contact with wood is made, and then, back the
Threaded Rod out 1/4 turn.
Step #4: Thread a 3/8-16 x 2-3/4” threaded stud into each of
the eighteen locations. Thread stud in until contact with wood is
made; then turn back 1/4 turn.
FIGURE TWO