8.2 Controller Overview
Before general use, please follow these important commissioning steps:
Ensure boiler is connected to the mains water supply.
Turn on the mains power and press and hold the power button for 10 seconds. The boiler
should begin filling and heating.
Ensure boiler is set to 98˚C, fully drain the boiler contents from the tap and repeat. Boiler should
be fully drained twice before general use.