Fig. 50 — EconoMi$er
®
IV Wiring
Step 12 — Adjust Factory-Installed Options
SMOKE DETECTORS
Smoke detector(s) will be connected at the Controls Connec-
tions Board, at terminals marked “Smoke Shutdown”. Remove
jumper JMP 3 when ready to energize unit.
ECONOMI$ER IV OCCUPANCY SWITCH
Refer to Fig. 50 for general EconoMi$er IV wiring. External
occupancy control is managed through a connection on the
Central Terminal Board.
If external occupancy control is desired, connect a time clock or
remotely controlled switch (closed for Occupied, open for Unoc-
cupied sequence) at terminals marked OCCUPANCY on CTB.
Remove or cut jumper JMP 2 to complete the installation.
Step 13 — Install Accessories
Available accessories include:
• Roof curb
• Thru-base connection kit (must be installed before unit is
set on curb)
• Manual outside air damper
• Two-position motorized outside air damper
• EconoMi$er IV (with control and integrated barometric
relief)
• EconoMi$er2 (without control/for external signal and inte-
grated barometric relief)
• Power exhaust
• Differential dry-bulb sensor (EconoMi$er IV)
• Outdoor enthalpy sensor
• Differential enthalpy sensor
• Time Guard II compressor anti-cycle control
• Outdoor coil hail guard
• Outdoor coil protector grille
• Head pressure control
• Programmable setback thermostat
• Electro-mechanical thermostat and subbase
• Thermidistat™ device
• Humidistat
• Electric heaters
• Single point kits
• Thermostat / sensors
•CO
2
sensor
• DDC interface (PremierLink™ controller)
• Louvered hail guard
• Phase monitor control
Refer to separate installation instructions for information on in-
stalling these accessories.
Step 14 — Check Belt Tension
Measure the belt span length as shown in Fig. 51. Calculate the
required deflection by multiplying the belt span length by
1
/
64
.
For example, if the belt span length is 32 inches:
32 x
1
/
64
=
1
/
2
-in. deflection.
BELT FORCE — DEFLECTION METHOD
Check the belt tension with a spring-force belt force deflection
gage (available from drive belt manufacturer).
1. Place a straightedge along the belt between the two pul-
leys. Measure the distance between the motor shaft and the
blower shaft.
2. Set the tension gage to the desired tension (see Table 1 in
Fig. 51). Place the large O-ring at that point.
3. Press the tension checker downward on the belt until the
large O-ring is at the bottom of the straightedge.
4. Adjust the belt tension as needed.
Adjust belt tension by loosing the motor mounting plate front bolts
and rear bolt (see Fig. 52) and slide the plate towards the fan (to
reduce tension) or away from the fan (to increase tension). Ensure
Economizer 2 Position Damper
Unit Without Economizer or