860660202 Rev. B www.commscope.com
Instruction Sheet
© 2021 CommScope, Inc. All Rights Reserved Page 4 of 9
6. Powered Fiber Cable (PFC) Termination and Closeout
Step 1 – Route and terminate incoming/indoor Powered Fiber Cable (PFC)
1. Route the incoming PFC into the TB and secure to the strain relief bar with a supplied cable
tie, as shown in Figure 4. Ensure adequate length for fiber slack (1-1.5 meters).
2. Strip the outer jacket of the PFC using a round cable stripper so that there is approximately
25mm of jacket extending inside the box, as shown in Figure 5. Trim any strength members
or other cable components except for power conductors and fibers.
Figure 4 Figure 5
APPROX. 25mm OF
CABLE JACKET