7.3.Wheretouse
The grinder should be installed on a at, stable surface. The minimum
dimensions of the work space should be as follows:
Model
F10 MASTER CONIC OD F10 FRESH, F8 OD
Height
29.53
750
26
670
in
mm
Width
9.05
230
9.05
230
in
mm
Depth
16.75
420
16.75
420
in
mm
7.4.Grinderinstallation
Before grinder installation, the following should be considered:
• Thegrinder informationplaque datacoincides withtheelectricalsystemon
site.
• Theelectricaloutletcoincideswiththegrinderplug.
• The electric power at the location of installation should meet the minimum
requiredtoproperlyrunthegrinder.
• Theinstallationsiteshouldhavetheproperelectricaloverloadprotections.
• Thegrindershouldbeproperlygroundedasspeciedbylocalcode.
NOTE: The grinder should be used in environments with mínimum temperature
of 77-86F and should not be installed in places (such as industrial kitchens) where
cleaning is done with direct water spray cleaning.