ESIE11-02 Pre-Test Run Checks
Part 4 – Commissioning and Test Run 4–3
3
4
5
1
Part 4
1 Pre-Test Run Checks
1.1 What Is in This Chapter?
Introduction This chapter contains checks you have to carry out before every test run.
Overview This chapter contains the following topics:
Topic See page
1.2–General Checks 4–4
1.3–Water Piping Checks 4–5
1.4–External Static Pressure: EUWA*5-24KBZW1 4–8
1.5–External Static Pressure: EUWY*5-24KBZW1 4–10
1.6–Static Pressure of the Pump for EUWA*5-24KBZW1 and EUWY*5-24KBZW1 4–12
1.7–Water Pressure Drop through Evaporator: EUWA*5-12KBZW1 4–14
1.8–Water Pressure Drop through Evaporator: EUWA*16-24KBZW1 4–16
1.9–Water Pressure Drop through Evaporator: EUWY*5-12KBZW1 4–18
1.10–Water Pressure Drop through Evaporator: EUWY*16-24KBZW1 4–20
1.11–Electrical Checks 4–22
1.12–Control of the function of the 4-way valve for EUWY*5-24KBZW1 4–23