12 | Commissioning
Installer reference guide
54
RXTM30+40N2V1B + RXTP25+35N2V1B9 + RXTP25+35N2V1B8 +
ARXTP25+35N2V1B + RXTA30N2V1B
R32 split series
4P518023-7H – 2020.08
12 Commissioning
In this chapter
12.1 Overview: Commissioning ...................................................................................................................................................... 54
12.2 Precautions when commissioning.......................................................................................................................................... 54
12.3 Checklist before commissioning............................................................................................................................................. 54
12.4 Checklist during commissioning ............................................................................................................................................. 55
12.5 To perform a test run ............................................................................................................................................................. 55
12.6 Starting up the outdoor unit .................................................................................................................................................. 56
12.1 Overview: Commissioning
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1 Checking the "Checklist before commissioning".
2 Performing a test run for the system.
12.2 Precautions when commissioning
DANGER: RISK OF ELECTROCUTION
DANGER: RISK OF BURNING/SCALDING
CAUTION
Do NOT perform the test operation while working on the indoor units.
When performing the test operation, NOT only the outdoor unit, but the connected
indoor unit will operate as well. Working on an indoor unit while performing a test
operation is dangerous.
CAUTION
Do NOT insert fingers, rods or other objects into the air inlet or outlet. Do NOT
remove the fan guard. When the fan is rotating at high speed, it will cause injury.
During test operation, the outdoor unit and the indoor units will start up. Make
sure that the preparations of all indoor units are finished (field piping, electrical
wiring, air purge, ...). See installation manual of the indoor units for details.
12.3 Checklist before commissioning
After the installation of the unit, first check the items listed below. Once all checks
are fulfilled, the unit must be closed. Power-up the unit after it is closed.

Table of Contents

Other manuals for Daikin RXTP25N2V1B8

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin RXTP25N2V1B8 and is the answer not in the manual?

Daikin RXTP25N2V1B8 Specifications

General IconGeneral
BrandDaikin
ModelRXTP25N2V1B8
CategoryAir Conditioner
LanguageEnglish

Related product manuals