INSTALLATION PROCEDURE
WARNING: Possible Fire Hazard
Do Not plug into main service equipment on power pole.
Do Not use extension cords
8. FINAL BACK FILLING
Back ll should be mounded above grade slightly to allow for settling. Tamp the back
ll beneath the inlet, outlet and air piping to provide good support.
9. TRIM INSPECTION RISERS
Trim inspection risers to proper length. The 4” aeration inspection riser also serves as a
vent for the tank.
Caution: The bottom of the 4” aeration riser must be above the water level for
both visual inspection and ventilation. Both of the optional 6” and 4” top caps
must be above ground level to prevent ground water from entering the risers.
Caution: Care must be taken not to push the optional 6” Clarier Inspection Riser
down too far. This may cause damage to the euent discharge tee assembly and
the clarier.
Caution: Maximum burial depth - 2 feet from top of tank ange with dome or
24” manways and 1 foot from top of tank ange with at lids. For burial depths
beyond 2 feet contact the factory.
STEP 8
STEP 9