Operation Overview - 28 FX20 Operator’s Manual
Planning
CMW
Planning
1. Gather information about jobsite (page 32).
2. Inspect jobsite (page 33).
3. Check supplies and prepare equipment (page 35).
Setting Up at Jobsite
1. Prepare jobsite (page 34).
2. Position vacuum excavation unit.
3. Leave unit hitched to towing vehicle or properly stabilized if trailer-mounted unit.
4. Block trailer wheels if trailer-mounted unit.
Vacuuming
1. Connect hoses (page 44).
2. Start unit (page 44).
3. Remove debris (page 45).
4. Disconnect hoses.
5. Drain tank (page 48).