Delivery and Inspection
Upon arrival inspect equipment and report any damage to delivery carrier. File any damage claims with the delivery carrier.
Request a written inspection report from the Claims Inspector to substantiate all damage claims.
Compare the equipment received with the description of product ordered. Report any incomplete shipments to the delivery carrier
and your Donaldson Torit representative.
Unloading and Positioning
Equipment should be lifted only by qualied crane or fork truck operators.
Failure to lift the equipment correctly can result in severe personal injury and/or property damage.
1. Remove any crates or shipping straps.
2. Lift the packaged collector from transport container.
3. Inspect for any damage and/or missing parts and report to freight carrier.
4. Check for any hardware which may have become loose during shipment and tighten as necessary.
Installation
Location and Site Selection
Electrical Installation (including bonding and grounding of the collector) must be performed by a qualied electrician.
Do not install in classied hazardous atmospheres without an enclosure rated for the application.
Service must be performed by trained and qualied maintenance personnel.
This equipment may start or stop unexpectedly from a remote location.
Codes may regulate recirculating ltered air in your facility. Consult with the appropriate authorities having jurisdiction
to ensure compliance with all national and local codes regarding recirculating ltered air.
Equipment location must conform to all codes and standards, should be suitable fot the type of dust being handled and should
ensure easy access for service and utility connections. Site selection must account for wind, seismic zone and other load
condidtions.