1
600 A, 15 kV, 25 kV and 35 kV Class Insulated Standoff Bushing
InstallatIon and operatIon InstructIons MN650036EN November 2016
Product information
WARNING
All associated apparatus must be de-energized during
installation or maintenance.
CAUTION
Eaton’s Cooper Power series 600 A Insulated Standoff
Bushing is designed to be operated in accordance with
normal safe operating procedures. These instructions
are not intended to supersede or replace existing
safety and operating procedures. The insulated standoff
bushing should be installed and serviced only by
personnel knowledgeable of good safety practices and
fully trained on the installation and application of high
voltage electrical equipment.
NOTE: For product applications that require ratings or
characteristics not shown, contact Eaton for specific
recommendations.
Introduction
Eatons Cooper Power series 600 A, 15 kV, 25 kV and 35
kV Insulated Standoff Bushing meets the full requirements
of ANSI
®
/IEEE Standard 386
— Separable Insulated
Connector Systems, and provides a single deadbreak
interface made of high-quality insulating epoxy material. It
is used in pad-mounted cabinets, underground vaults and
other apparatus to isolate and sectionalize an energized
cable. The Insulated Standoff Bushing is designed to be
installed in the parking stand mounted on a transformer
or other apparatus. A grounding lug is provided on the
standoff bracket for attachment of a ground wire to ensure
deadfront construction. The bushing provides a fully
shielded, submersible connection for deadbreak operation.
All standoff bushing brackets have a stainless steel eyebolt
with a brass pressure foot. The bushing body is bolted to
a stainless steel base bracket using a stainless steel bolt.
Special pins ensure firm location of the bushing on the
bracket.
Insulated standoff bushing kit
Each kit contains:
Insulated Standoff Bushing
Lubricant
Instruction Sheet
Figure 1.
Typical 15 kV and 25 kV Class Standoff shown.
Installation
Ground
Attach ground drain wire from bushing ground lug to system
ground.
Clean and lubricate
1. Remove protective shipping cap.
2. Clean and lubricate bushing interface using lubricant
supplied or approved equivalent.
Install
1. Grasp eyebolt on standoff bushing using hotstick.
2. Install standoff bushing on parking pocket using
hotstick.
3. Use hotstick to turn eyebolt clockwise until tight to
ensure rigid mounting.
ote:N 600 A standoff bushings are designed to fit standard
parking pockets furnished with most apparatus.
Operation
1. Disconnect connector from apparatus bushing following
connector operating instructions.
2. Position connector on standoff bushing.
3. Thread connector stud clockwise into standoff bushing
until It is tightly seated.
4. Cover de-energized bushing with a 600 A grounded
insulated protective cap or 600 A bushing adapter with
200 A insulated protective cap.
ote:N 600 A standoff bushing interface must be covered at
all times when not in use, using either the shipping
cap (if de-energized) or an insulated protective cap (if
energized).