600 A T-OP II™ terminator operation instructions
1 Operation Instructions MN650047EN May 2017
CAUTION
Eaton’s Cooper Power series 600 A T-OP II™ terminator
is designed to be operated in accordance with normal
safe operating procedures. These instructions are not
intended to supersede or replace existing safety and
operating procedures. Terminators must be de-energized
during operation or maintenance. Visible break and
adequate grounding must be provided before cable
work proceeds.
T-OP II terminators should be installed and serviced only
by personnel familiar with good safety practice and the
handling of high-voltage electrical equipment.
General
Equipment required
1 Voltage Tester
3 Grounding Elbows
3 T-OP II insulated Standoff Bushings
3 T-OP II insulated Protective Caps
1 Hotstick
Personal Protective Equipment
Insulating Rubber Blanket
Silicone Grease
Figure 1. 600 A T-OP II Terminator
Figure 2. One-line diagram of a three-phase cable connected to a three-phase switch on either end
200 A PROTECTIVE CAP
LOADBREAK TAP
REDUCING PLUG
(LRTP)
URD CABLE
T-OP II TERMINATOR ASSEMBLY
APPARATUS BUSHING
Figure 3. Line illustration of the T-OP II