VCS/VMS Auxiliary Section Assembly and Installation | Auxiliary Section Service Procedures TRSM0940
17. . Install the 15/16” nut to secure the range yoke bar. 
Torque to 70-85 lb-ft. 
18.  Install the 3/4” nut that secures the reduction yoke bar. 
Torque to 50-65 lb-ft.
19. Position a new gasket on the Combination Cylinder 
mounting surface. Install the Combination Cylinder 
Cover. Apply Eaton® Sealant #71205 or equivalent to 
the five (5) retaining cap screws and torque to 35-45 
lb-ft.
20. Attach the Auxiliary Section lifting bracket to the top of 
the Auxiliary Case.
21. Position a new Auxiliary Case Gasket on the mounting 
surface of the Main Case.
22. Install the Auxiliary Case Assembly onto the transmis-
sion Main Case dowel pins. Using the Output Shaft, 
wiggle the auxiliary case forward until it is as far for-
ward as possible. Remove the auxiliary section lifting 
bracket.