Pre-Installation Checklist
Learn the steps that you need to follow before installing the 4120C appliance.
About This Task
When you receive the appliance, ensure that you have all the necessary parts before installing the
appliance.
Procedure
1. Verify the box contents. The box contains the following items:
• One 4120C Quick Reference Guide
• One 4120C appliance
• Two shipping lock screws
• One AC power cord bracket and retention strap kit
• One rack mounting kit
• One front panel faceplate
• One rail kit installation instruction sheet
Note
The power cord needs to be purchased separately for the respective deployment country.
They can be ordered at https://www.extremenetworks.com/powercords.
2. Visually inspect the appliance for any physical damage.
Contact Extreme Networks Support Portal if there is any damage.
3. Review the Safety Guidelines.
Extreme Networks Universal Compute Platform Appliance 4120C
11