The G8 control DC Panel receives the signals sent from your switch panels and
performs the actions that have been requested by activating and deactivating
the required circuits.
Every circuit controlled by the G8 is numbered and listed on a black label (load
list) which is usually mounted next to the G8 panel.
A corresponding numbered LED will illuminate
green whenever a particular circuit is on. For instance, if
you press the Bath Light button on your switch panel, the
green LED for output 11 will illuminate and the Bath Light
will turn on (Fig 3).
Testing output voltage using a Multi-meter.
Ensure that the G8 circuit is on and that the corresponding green LED is illuminated.
To test the output voltage for the Ceiling Lights example, touch the positive lead to the output
pin for output 11 (Connector J9 – Pin 1) and the negative lead to the ground stud (as pictured
below).