02-09
2-5-3 Defrost Operation Control
Accumulated heating operation time is 40 minutes or longer
[Accumulated heating operation time is reset at the end of cooling operation or defrosting operation.]
and
an outdoor unit satisfies condition or below
Condition : "Heat exchange temperature -2°C" accumulated operating time is 180 minutes or longer
Condition : After the following all condition satisfied, "heat exchange temperature defrosting start judgment
temperature and during heat exchange liquid temperature drop" accumulated time:10minutes
(a) accumulated heating operation time 30 minutes
(b) 10 minutes have elapsed after outdoor unit starting
(c) 5 minutes have elapsed since oil recovery
* Defrosting start and end judgment temperature are determined by the outdoor temperature.
Defrosting start judgment temperature = 0.8 x outdoor temperature - 11.6 (However, -27.6°C to - 6°C)
At all outdoor units, heat exchange liquid temperature end judgment temperature
or
when 15 minutes have elapsed from the start
Defrosting end judgment temperature = 0.39 x outdoor temperature + 12.7 (However, 5 to 12°C range)
If the calculated result is lower than -27.6 , the judgment temperature is defined as -27.6
If the calculated result is higher than -6 , the judgment temperature is defined as -6
2-5-2 Pre-heat Operation
This pre-heat operation protects the start up failure by preventing the refrigerant from soaking into the oil in compressor.
Crankcase heater ON: 30 minutes elapsed since installed compressors stopped
(However, ON when power turned on)
*It doesn't control according to the temperature.
If the calculated result is lower than 5 , the judgment temperature is defined as 5
If the calculated result is higher than 12 , the judgment temperature is defined as 12
OFF: Compressor starts
Outdoor temperature <2 and Compressor stop count exceed 20 times at less than 10 minutes of accumulated
heating operation time
Defrost Operation Start Condition 1
Defrost Operation Start Condition 2
Defrost Operation End Condition

Table of Contents

Other manuals for Fujitsu AUXB07GALH

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fujitsu AUXB07GALH and is the answer not in the manual?

Fujitsu AUXB07GALH Specifications

General IconGeneral
BrandFujitsu
ModelAUXB07GALH
CategoryAir Conditioner
LanguageEnglish

Related product manuals