Installation steps:
Chapter V: How to Install the ATO
Target water level
Step 1:
Install the ATO controller on the tank wall
and align the target water level between
"LOW" and "MID".
Step 2:
Manually fill the water close to the “Low”.
Neither exceed the middle line of the “LOW”
and “MID”, nor lower more than 1cm of the
LOW light.
Note:
The initial water level will affect the calculation
of the SPT period.
Not exceed the middle line of
the “LOW” and “MID”
Not lower more than 1cm of
the low light