GE MEDICAL SYSTEMS CT PROSPEED SERIES INSTALLATION
2124011
3-25
REV 15
3–5–2 Check Out
Note
Total processing time from test start to system ready is approximately 14 minutes.
1. Verify
that the system starts up normally with no errors during the P–ON test Level 2 self test. Initialize an MOD
cartridge, and Archive and Retrieve a few images to ensure the system is working properly.
To run the P–ON test level 2, refer to the following procedure;
a. On the CPW Board (slot #1), set the Dip SW 8A1 as follows:
ON
12345678
ON : 1
OFF: 0
SW 8A1
b. Turn
ON the OC power
. It takes approx. 14 minutes for the P–ON test level 2 to finish.
The start up screen will
appear when the P–ON test has been completed normally.
c. After verification of the P–ON test level 2, set the SW 8A1 to the default setting.
ON
12345678
ON : 1
OFF: 0
SW 8A1
Note
There
is no need to turn OFF the OC power when the SW8A1 setting is changed.
The new setting is
available at next power ON sequence.
2. Install the OC front cover.
3. Switch
ON the OC power
. V
erify that the system starts up with no errors and also verify that the W/R indicator of
the MOD Unit flashes on and off.
4. Verify
that files can be saved and retrieved from the MOD. Refer to the Operator Manual and for the correct MOD
System Initialize, Archive, Retrieve and Operations.