GMV DC Inverter VRF 
52 
Description of each stage of debugging progress 
10_Status 
judgments of 
outdoor valves 
before startup 
Outdoor valves are being turned on. 
Outdoor valves are not fully turned on. 
Outdoor valves are turned on normally. 
11_Calculate 
refrigerant 
quantity 
manually 
Calculate the refrigerant quantity 
manually and confirm the perfusion 
status of refrigerant (the quantity of 
refrigerant added into the system must 
be recorded accurately). 
12_Confirm 
debugging 
startup 
Ready for units to start debugging. 
Manual calculation of refrigerant 
quantity is set up. 
Debugging is enabled in cooling mode 
(debugging mode, auto-selected by 
system).   
Error occurs during debugging in 
cooling mode. 
Error of other modules occurs during 
debugging in cooling mode. 
Outdoor pipeline and valves are not 
normal. 
System detects error in indoor pipeline. 
XXXX is the project no. of the faulted 
IDU. 3s later, error code U8 is 
displayed. For example, IDU no. 100 
has U8 error, then LED3 displays like 
this: 01 (2s later) 00 (2s later) U8, and 
repeat again. 
Debugging is enabled in heating mode 
(debugging mode, auto-selected by 
system). 
Error occurs during debugging in 
heating mode.   
Error of other modules occurs during 
debugging in heating mode. 
Outdoor pipeline and valves are not 
normal.   
System detects error in indoor pipeline. 
XXXX is the project no. of the faulted 
IDU. 3s later, error code U8 is 
displayed. For example, IDU no. 100 
has U8 error, then LED3 displays like 
this: 01 (2s later) 00 (2s later) U8, and 
repeat again. 
Debugging is finished. System is on 
standby condition. LED1 displays 
module address. LED2 and LED3 
display “OF”.