GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 
175 
 
If this fault occurs, the number of the new AP1 is identical to that of a unit within the network. Manually 
change it to the original number of the faulty AP1 or a unique number. There are three methods to 
change project number: 
Method 1: If the IDU is configured with wired control, set P42 to a new project number.   
Method 2: If the IDU is configured with lamp board, use the special control YV1L1 to set P42 to a new 
project number. 
Method 3: If the IDU is configured with the Debugger, configure a new  project number through this 
software.   
Tip: 
If there are N units within the network, the units should be numbered from N+1.   
Special situation: 
In some cases, the created project number is identical to that of a unit within the network. In this case, 
you  can  use  the  ―one-key  IDU  project  number  reset‖  function.  However,  this  function  will  cause  the 
project number of the entire system to be re-distributed; thus, original number will be changed. If you do 
not expect this result, forbid the use of this function and replace the AP1 again.   
Methods to use the ―one-key IDU project number reset‖ function: 
Method 1: If the IDU is configured with wired control, set P45 to reset IDU project number through one 
key function. 
Method 2: If the IDU is configured with lamp board, use the special control YV1L1 to set P45 and reset 
IDU project number through one key function. 
Method 3: On the AP1 of the master ODU, press and hold SW5 for 10 seconds at least to clear all 
project  numbers  of  the  IDUs  and  then  redistribute  project  numbers.  Other  parameters  are  kept 
unchanged.