33
© Copyright, GREE Canada, 2021 © Copyright, GREE Canada, 2021
130cm
40cm
• Correct installation is shown in figure below (when installing it through a
wall, height of air outlet should be about 40-130cm above floor).
• Wrong installation is shown in following figure (If the pipe is bent too much,
it would easily cause malfunction.)
1. Remove joint A:
Press the clasp and lift joint A
upwards to remove it.
Clasp
Upward
Joint A
Joint A
Heat discharge pipe
Anticlockwise
Disassemble
2. Remove heat discharge pipe
from protective grille
sub-assy.
Disassemble heat discharge pipe