3.4 Unit Installation Requirements
(1) Ensure that the sound and air flow of unit operation will not affect others or
animals and plants.
(2) Ensure that the unit has good ventilation. If a canopy is installed to protect the
unit, the heat dissipation and absorption shall not be affected.
(3) The unit shall be installed at a place with a solid foundation. The unit shall be
installed vertically more than 15 cm above the horizontal ground, and shall be
fully firmly installed with the impact of strong wind, typhoon and earthquake
fully considered.
(4) The wooden base with the unit should be removed when conducting
installation.
(5) We recommend sheltering the unit to avoid the possibility that snow
accumulates and damages the evaporator.
(6) Drainage ditch should be reserved next to the unit for condensate discharging
as well as evacuating water for disuse in winter.
(7) If the unit is installed in a place that does not require drainage, it is
recommended that all drainage holes be unblocked. Special attention should
be paid to: at this time, the water discharge from the drainage holes are easy
to freeze in the temperature below 0, please set up warning signs or
isolation fences at the unit install site to avoid unnecessary injures such as
sliding.