24
Cut the corresponding pagoda connector using a utility knife, route the AC input power cable
through the cable hole at the bottom, and connect the cable to the AC circuit breakers.
No.
Meaning
1
Screw assembly
2
Spring
washer
3
(Optional) Large
washer
4
Wiring terminal
5
Copper bar
6
Flat washer
Installing the Four-core AC Input Power Cable
Installing AC Input Power Cables
5.5
1. Pre-install bolts according to the recommended torque of 27 m.
2. Verify that the torque of the installed bolts is 27 m using a torque wrench.
3. Mark the bolts whose torque has been verified using a marker.
When connecting AC input power cables, ensure that the cables are not damaged. Ensure
that the neutral wire is securely connected. Otherwise, AC power devices in the system may
be damaged.
The figures in the procedure for installing AC power cables use one of the LUNA2000-
2.0MWH-1HX models as an example.