Installing the Cabinets
Installing the Base
a
52-60 mm
90°
Φ16
Cast a concrete pad.
Mark the anchor points for the base.
Drill the holes by using a hammer drill.
Concrete pad
The height of the concrete pad must meet the heat-dissipation and waterproofing requirements of the
cabinet. The concrete pad must be 200 mm higher than the ground, and the horizontal error must be less
than 5 mm when the pad is cast.
Do not use the base as a positioning tool when drilling. Otherwise, the paint on the base may be scratched.
Concrete pad
Unit: mm
CAUTION