congurations in the table are complete and meet the requirements of the
company.
Cause ID=5:
1. Check whether the communication network between the SmartLogger and
the plant scheduling control system is normal.
2. Check whether the reactive power scheduling commands received by the
SmartLogger from the plant scheduling control system are correct, such as
the command format and protocol type.
3. When "Reactive power control mode" is set to "Remote dispatch" and the
"Shut down array upon reactive power signal timeout" function is not needed,
you are advised to disable the function.
SmartLogger3000
Alarm Reference
3 1101 Reactive Power Scheduling Instruction
Exception
Issue 01 (2023-09-15) Copyright © Huawei Technologies Co., Ltd. 5