1. Remove the fasteners that secure the base to the transportation vehicle based on the site
requirements.
Item Reference
UPS UPS5000-H-(1200 kVA–1600 kVA) User Manual (100 kVA Power Module)
ECC800 ECC800 Data Center Controller V100R021C10 User Manual (for ECC800-Pro)
Installation dimensions (unit: mm)
01
Reference Documentation
2.4 MW PowerPOD base dimensions
Before installation, read the user manual carefully to get familiar with product information and
safety precautions, The 2.4 MW PowerPOD is used as an example to describe the installation and
commissioning.
2. Determine the position for installing the PowerPOD on the floor based on the mounting holes
on the platform base. Drill holes and install expansion sleeves.
1. Adjust the PowerPOD in the installation direction, connect the steel hoisting ropes, and
hoist the PowerPOD at the entrance of the unloading area.
2. When unloading the PowerPOD, use a crane to
hoist one end of the PowerPOD into the room to
place it on the moving dolly at the entrance of
the unloading area, and place the other end on
the wood sleeper. Use a crane to lift the
PowerPOD end placed on the wood sleeper, and
use an electric winch to slowly push the
PowerPOD into the room.
3. After the winch pulls the PowerPOD into the
room, place the moving dolly at the rear of the
PowerPOD.
4. After moving to the installation position, place
the jacks at the I-shaped steel positions on the
base of the PowerPOD. Lift up the PowerPOD
and remove the tank wheel, and then put down
the jacks.
1. Place the PowerPOD on the hoisting platform and bind it.
2. Adjust the prefabricated PowerPOD in
the installation direction, connect the
steel hoisting ropes, and hoist the
PowerPOD at the entrance of the
unloading area.
3. Connect the steel hoisting ropes to the
rectangular hoisting tool.
4. Conduct trail hosting. Lift the hook by about 200 mm under the command of the crane
operator and keep it for 5 minutes. Check the status of the crane, legs, and steel ropes.
If any exception is found, put down the PowerPOD immediately and rectify the fault
until the potential risk is eliminated.
5. Lift the PowerPOD to the hoisting hatch, place the front part of the hoisting platform
indoors, and secure the hoisting platform using two manual hoists.
2.4 MW indoor PowerPOD
Binding strap
Hoisting
platform
03
Hoisting on the First Floor
02
Installation Preparations
04
Hoisting on a Higher Floor
Winch Pulling
rope
Moving
dolly
Wood
sleeper
Pallet truck
Moving dolly
05
Securing a PowerPOD
Manual hoist
Hoisting platform
PowerPOD
Hardware Installation
(1) Transformer