Horizontal Right-Side Vent
Single Pressure Switch Detail
TrapConnection
Preassemble&
insert intofurnace
ReliefTube
BlackRubber 3/16" -....
(4.8mm)ID ....
FlexibleTubing Connector3/16'P .....................
(4.8mm)OD (Loose PartsBag)
ReliefTubeExtension ..................
BlackRubber3/16" (4.8mm)ID
Cutto Fit(LoosePartsBag)
Dual Pressure Switch _;
Plastic Cap
Yellowor black
/
/
VentDrain
&Clamps
Level or Sloped
towardsTee
J
/
lemoveKO be1
inting Trap
DrainTube
BlackRubber
112"(12.7mm)ID
& Clamps
Coupling&Clamps
(Optional)
Field
SuppliedTee
'_ _Tee Trap
,_J WhitePVC
! _ (loosepartsbag)
-- ElbowTubeBlack Rubber
1/2"(12.7mm)ID &Clamps
(LoosePartsBag)
On SomeModels
ONLY
Alternate Orientation
BarbedCoupling1/2" (12.7mm)
OD(Loose PartsBag)
25-24-70c
Representative drawing only_some models may vary in appearance,
Horizontal Right-Side Vent (SeeFigure19)
Disconnect drain tee if installed (N9MPD and *9MPD models only)
Disconnect the hoses from the trap assembly, and remove trap
and trap mounting bracket from the blower compartment. Using
cover plate and gasket provided in the loose parts bag, cover the
hole from the burner compartment to the blower compartment and
secure with screws.
Remove knockout from the side of the furnace casing where drain
tube will exit.
Mount the trap externally to the bottom side of the unit using the
two screws provided in the location shown.
Cut the corrugated tube as shown in the illustration above.
Connect the corrugated hose from the transition to the trap.
Secure connections with clamps.
Connect the black 1/2" (12.7mm) ID drain tube from the Vent Drain
to the trap. If an extension is required, use the 1/2" (12.7mm) OD
barbed coupling and the black 1/2" (12.7mm) ID drain tube in the
loose parts bag. Cut tube to length. Secure connections with
clamps.
Connect the 3/16" (4.8mm) ID relief tube to the middle port on the
trap. If an extension is required, use the clear 3/16" (4.8mm) OD
splice connector and the black 3/16" (4.8mm) ID relief tube in the
loose parts bag. Cut tube to length.
Cut an appropriate length of 2" (50.8mm) PVC pipe, fittings and
extension pipe long enough to exit the cabinet and connect the
vent drain to either:
A standard field supplied 2" (50.8mm) PVC tee (N9MP1 or
N9MP2 models), or
A 2" (50.8mm) PVC coupling fastened onto the drain tee
(N9MPD and *9MPD models)
Install tee trap into bottom section of tee.
Important: The pipe to the tee trap must be level or sloping towards
the tee trap
Connect the tee trap and the main drain line exiting the casing as
shown in Figure 20.
Note: It is recommended that all PVC piping and fitting
connections be fit up and inspected before final cementing. Both
the external trap and the external tee trap must be primed
before operation, Verify all condensate drain connections are
securely clamped. A coupling and clamps (in loose part bag) may
be installed as shown for future servicing of the vent system.
440 01102404