20
INSTALLATION
isar - Installation and Servicing
FLUE OUTLET
21
FITTING THE PIPING FRAME AND VALVES (Rear Flue outlet shown)
TO FIT THE PRE-PIPING FRAME DIRECTLY TO THE WALL
Insert wall plugs.
Put the screws into the wall plugs and leave 10mm proud
Hang the frame onto the screws (take care to use the
same hole position from each group as previously chosen
with the wall template) and tighten up.
Locate the support bracket on the piping frame.
Note. Service connections may be made now, before mounting the boiler, if required. Refer to Frames 32-34.
Piping
frame
Wall
plug
Screw
(10mm proud)
Support
bracket
nm8443
Note. Isolating valves are supplied separately in the hardware pack box.
Fit to the piping frame BEFORE mounting the boiler.
Piping
frame
Wall
plug
Screw
(10mm proud)
Support
bracket
nm8444
TO FIT THE PRE-PIPING FRAME USING THE STAND-OFF FRAME
OPTION KIT (To allow pipework to be taken upwards)
Put the screws into the wall plugs and leave 10mm proud.
Hang the stand-off frame onto the screws and tighten up.
Fasten the piping frame to the stand-off frame with the
6mm screws provided.
Locate the support bracket on the piping frame.
Note.
If the clearances above and below the boiler are less than
the length of the pipes it will be necessary to position the
pipes behind the wall mounting plate BEFORE the plate is
screwed to the wall.
nm8453
Valve securing
clip 15mm
Valve securing
clip 22mm
Valve securing
clip 22mm
Isolation valve
c/w pressure
gauge
Bulkhead
connector
Compression
gas cock
Restrictor
valve
Isolation valve
c/w drain
1. Remove valves and clips from
the hardware pack box.
2. Assemble valves to the frame
and secure in place with clips
provided.
3. Make sure to fit valves in
correct order shown.
203319-3.pmd 27/03/2008, 08:1520

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IDEAL isar HE24 and is the answer not in the manual?

IDEAL isar HE24 Specifications

General IconGeneral
Boiler TypeCombi
Central Heating Output24kW
DHW Flow Rate9.8 l/min
MountingWall Mounted
Domestic Hot Water Output24 kW
ERP RatingA
Output24 kW
Central Heating Flow Temperature Range30-80°C
Dimensions700 x 395 x 278 mm
Warranty2 Years
Fuel TypeNatural Gas
Efficiency RatingA Rated