Maintenance Summary - 4.000 Operating hours
It is recommended to document the maintenance activities carried out by using the appropriate
maintenance log. The maintenance log has the document number LR1702.10191 - 05.06.2019.
D010 - Cleaning of the machine
D020 - Check the pressure accumulator
D050 - Check the lubrication system
D060 - Check the pneumatic system
D077 - Check tool clamping sets of the milling spindles (from Berg)
D095 - Check main and counter spindles
D125 - Replace cooling lubricant adapter (HSK tool mountings)
D170 - Check the system for reconditioning the cooling lubricant
D180 - Check fire extinguishing system (visual inspection)
D330 - Replace belts and check belt tension
D370 - Check and potentially replace the end position dampers
D440 - Replacing hydraulic fluid
D500 - Perform data backup
D520 - Check control cabinet and cable assemblies (visual inspection)
D640 - Check setting of electrical fuses
Maintenance Summary - 4.000 Operating hours
74
Maintenance Instructions
R200
LR1702.10181 - 05.06.2019