Verify the following check list before commissioning the LATENTO XXL.
Start running the LATENTO XXL only when you can answer all questions
with "yes".
Has the container been sufficiently filled with water? Yes No
Has the solar heat exchanger been correctly connected? Yes No
Has the reheating heat exchanger (heating circuit) been
correctly connected? Yes No
Has the heating heat exchanger (boiler circuit, optional)
been correctly connected? Yes No
Has the DHW heat exchanger been correctly connected -
including shut-off valves and pressure-rinsing connections? Yes No
Is the pipework complete and correct acc. to the installation
proposal? Yes No
Are the heating circuits filled and bled? Yes No
Is the solar circuit filled and bled? Yes No
Are all temperature sensors installed at the right
position and connected to the regulation unit? Yes
No
Is the storage tank cover attached and closed tight? Yes No
When using the electrical heating element:
Is this element screwed tight in the cover and has been
connected by an expert? Yes No
Have all connection pipes and fittings been insulated
conforming to standards? Yes No
Are pumps and heat generator connected to the
regulation unit correctly? Yes No
9. Commissioning