Commissioning
Filling
First you must ensure that the pressure in the expansion vessel is the same as the setting of the
connections for water tightness including any factory made connections such as the immersion
-
system.
Indirect Units
Fill the primary circuit according to the boiler manufacturers’ commissioning instructions. Any addi -
tives used in the heating system water circulating through the cylinder coil must be compatible for
use with stainless steel cylinders.
Storage Temperature
-