Section 7
Electrical System and Components
Plunger
Pushed “In”
VOM Meter
Leads
12 volt Test Leads
Test 4. Solenoid Hold-In Coil/Contact Continuity.
Use an ohmmeter set to the audible or Rx2K scale, and
connect the two ohmmeter leads to the two large post
terminals. Perform the preceding test (3) and check
for continuity. See Figure 7-40. The meter should
indicate continuity, if no continuity is indicated the
solenoid should be replaced. Repeat test several times
to confi rm condition.
Figure 7-40. Testing Hold-In Coil/Solenoid Contact
Continuity.