507581-04Page 34  of  60 Issue 2128
Condensate Piping
This  unit  is  designed  for  either  right  or  left  side  exit  of 
condensate  piping  in  upow  applications.  In  horizontal 
applications, the condensate trap  must extend below the 
unit. An 8” service clearance is required for the condensate 
trap. Refer to Figure 52 and Figure 53 for condensate trap 
locations. Figure 59 shows trap assembly using 1/2” PVC 
or 3/4” PVC.
NOTE: If necessary, the condensate trap may be installed 
up to 5’ away from the furnace. Use PVC pipe to connect 
trap  to  furnace  condensate  outlet.  Piping  from  furnace 
must slope down a minimum of 1/4” per ft. toward trap.
1.  Determine which side condensate piping will exit the 
unit, location of trap, eld-provided ttings and length 
of PVC pipe required to reach available drain.
2.  Use  a  large  at  head  screw  driver  or  a  1/2”  drive 
socket  extension  and  remove  plug  (Figure  52)  from 
the  cold  end  header  box  at  the  appropriate  location 
on the side of the unit. Install provided 3/4 NPT street 
elbow tting into cold end header box. Use Teon tape 
or appropriate pipe dope.
3.  Install the cap over the clean out opening at the base 
of the trap. Secure with clamp. See Figure 59.
Figure 52. Condensate Trap and Plug Locations
(Unit shown in upow position)
CONDENSATE TRAP AND PLUG LOCATIONS
(Unit shown in upflow position)
Plug
(same on 
left side)
Trap
(same on 
right side)
1-1/2 in.
NOTE - In upflow applications where side return air 
filter is installed on same side as the condensate 
trap, filter rack must be installed beyond condensate 
trap or trap must be relocated to avoid interference.
4.  Install drain trap using appropriate PVC ttings, glue 
all  joints.  Glue  the  provided  drain  trap  as  shown  in 
Figure 59. Route the condensate line to an open drain. 
Condensate line must maintain a 1/4” downward slope 
from the furnace to the drain.
Do not use copper tubing or existing copper condensate 
lines for drain line.
   CAUTION
5.  Figure  54  and  Figure  55  show  the  furnace  and 
evaporator  coil  using  a  separate  drain.  If  necessary 
the condensate line from the furnace and evaporator 
coil can drain together. See Figure 57 and Figure 58.
Upow  furnace  (Figure  53)  -  In  upow  furnace 
applications the eld provided vent must be a minimum 
1” to a maximum 2” length above the condensate drain 
outlet connection. Any length above 2” may result in a 
ooded heat exchanger if the combined primary drain 
line were to become restricted.
Horizontal furnace (Figure 55) - In horizontal furnace 
applications the eld provided vent must be minimum 
4” to a maximum 5” length above the condensate drain 
outlet connection. Any length above 5” may result in a 
ooded heat exchanger if the combined primary drain 
line were to become restricted.
NOTE: In horizontal applications it is recommended to 
install a secondary drain pan underneath the unit and 
trap assembly.
NOTE: Vinyl tubing may be used for condensate drain. 
Tubing  must  be  1-1/4”  o.d.  X  1”  i.d.  and  should  be 
attached to the drain on the trap using a hose clamp.
6.  If unit will be started immediately upon completion of 
installation, prime trap per procedure outlined in Unit 
Start-Up section.
Condensate  line  must  slope  downward  away  from  the 
trap  to  drain.  If  drain  level  is  above  condensate  trap, 
condensate  pump  must  be  used.  Condensate  drain  line 
should  be  routed  within  the  conditioned  space  to  avoid 
freezing  of  condensate  and  blockage  of  drain  line.  If 
this is not possible, a heat cable kit may be used on the 
condensate trap and line. Heating cable kit is available in 
various lengths; 6 ft. (1.8 m) - kit no. 26K68; 24 ft. (7.3 m) - 
kit no. 26K69; and 50 ft. (15.2 m) - kit no. 26K70.