Page 45
First and second stage cooling operate independent of 
each other and can modulate back and forth according to 
the thermostat demand. 
First Stage Cooling (Low Capacity) 
1 -  Cooling demand initiates at Y1 at the thermostat. 
2 -   Voltage  from  terminal  Y  passes  through  S4 
high pressure switch, energizes K1 compressor 
contactor, passes through the low pressure switch 
(S87)  and  returns  to  common  side  of  the  24VAC 
power. 
3 -   K1  closes,  energizing  B1  compressor  and  B4 
outdoor fan. 
4 -   Solenoid  L34  is  not  energized  so  the  slider  ring 
remains open, limiting compressor to low capacity. 
Second Stage Cooling (High Capacity) 
Compressor  is  operating  in  rst  stage  cooling.  Second 
stage thermostat  demand sends  voltage to rectier  plug 
D4. D4 converts the AC voltage to DC voltage and ener-
gizes  L34  unloader  solenoid.  L34  closes  the  slider  ring, 
allowing the compressor to operate at high capacity.