DC Inverter Multi VRF System
29
Description of each stage of debugging progress
Code meaning and operation
method
Progress
Code
Code
Code
db On 10 On U6 On
Outdoor valves are not fully turned
on. Press main board’s SW6 button
and display shows “db 09 OC”. Then
check if the gas and liquid valves of
ODU are completely open. After
confirmation, press the SW6 button
again. Then compressor will start
running for about 2min to inspect the
db On 10 On OC On
Valves status is normal. Unit will
display as in the left for 2s and then
12_ Confirm
debugging
startup
db On 12 On AP Blink
Ready for units to start debugging.
Press main board’s SW7 button to
confirm startup of debugging. 2s
later, main board will display as
db On 12 On AE On
Startup is confirmed. After displaying
for 2s, system will choose
“15_Cooling debugging” or
“16_Heating debugging” according
to ambient temperature. If the
project requests to add refrigerant
but it is not complemented before
debugging, then refrigerant can be
added in this process through the
15_ Cooling
debugging
db On 15 On AC On
Debugging for cooling mode. If no
malfunction occurs for 20min when
compressor is running, then system
db On 15 On
Error
code
On
Malfunction occurs when debugging
for cooling mode. After all
malfunctions are eliminated, system
16_ Heating
debugging
db On 16 On AH On
Debugging for heating mode. If no
malfunction occurs for 20min when
compressor is running, then system
db On 16 On
Error
code
On
Malfunction occurs when debugging
for heating mode. After all
malfunctions are eliminated, system
17_ Debugging
finished
00 On AC/AH On OF On
The entire unit has finished
debugging and under standby-by