Power Up: NTP-003 363-205-401
Page 4 of 4 Issue 7, March 1997
DO ITEMS BELOW IN ORDER LISTED FOR DETAILS, GO TO
12.
NOTE:
The
AUG1 PRU
is required only if multiparty channel units
that require positive ringing current are to be installed in the
dual bank assemblies.
DLP-509Install
AUG1 PRU
in power shelf (if required).
DLP-51013. Install (if not previously installed) and check fuses in
BFU
(bank
fuse unit) in power shelf.
14. If powering a SLC Series 5 RT dual channel bank, continued with
Step
15
. Otherwise, proceed to Step
17
.
DLP-51115. Install and test
PCU
(power converter unit) in facility shelf.
16. Remove
PCU
. Repeat previous Step for each new dual channel
bank assembly.
17. Update records to indicate that RT supporting equipment has
been installed. When required, perform RT Turn Up TAB proce-
dures for the appropriate Feature Package.