CDA3000 Operation Manual
4-7
4 Commissioning
1
2
3
4
5
A
DE
EN
FR
IT
ES
FR
VFC commissioning, rotational
drive without encoder
Prerequisite:
Inverter module fully connected.
Recommended IEC standard motor (see section A-1) connected.
Control terminals wired according to
terminal assignment 2,
see page 3-14.
•A K
EYPAD or a PC with installed DRIVEMANAGER (version V2.3 or
higher) is connected. For operation see section 4.6 and 4.7.
Attention: Make sure the rotating drive in your machine cannot cause
any damage (e.g. overrunning its stop limit) during commis-
sioning.
Step Action Comment
1
Switch on the power to the
inverter module.
After power-up the inverter module per-
forms a self-test (lasting approx. 1... 3 s).
2
In subject area _15FC set parame-
ters
152-ASTER to ROT_1
ROT_1 = Control terminal assignment
Analog speed input,
MOP function
3
Check that your drive can be run
at the rotating field frequency and
with the ramps as per the factory
setting.
Rotating field frequency (FMAX) = 50Hz
with reference (R1) = 10 V
Acceleration ramp = 20 Hz/s
1)
Deceleration and stop ramp = 20 Hz/ s
1)
If this is not possible, change the
parameters shown adjacent.
Back-up the setting in subject
area _15FC with
parameter 150-SAVE.
Subject area/Parameter
FMAX _30OL 303 -FMAX1
Acceleration
ramp _59DP 590 -ACCR1
Deceleration
ramp _59DP 592 -DECR1
Stop ramp _59DP 594-STPR1
1
Close ENPO contact and set a low
reference value with pot R1.
ENPO active enables power stage.
2
Start drive by closing the STL or
STR contact.
STL = Start counter-clockwise
STR = Start clockwise
3
Check direction of rotation of motor
shaft.
If direction is wrong check motor
connection (phase sequence).
4
Brake drive by opening the start
contact.
Drive brakes down to a standstill.
5
Open ENPO contact.
ENPO inactive safely disables power
stage.
Commissioning is complete.
1) Factory setting from BG1
to BG5 (15 kW ) = 20 Hz/s, as
from BG6 (22 kW) to
BG8 = 5 Hz/s
Start drive
Remember to
save the set-
ting.
Call up subject area
_15FC
Select parameter
150-SAVE
Set parameter to
START and confirm