VC Pro VRF 50/60Hz 
    187 
Part 3 - System Design and Installation 
it may be necessary to run the system in cooling mode during the refrigerant charging procedure. In such circumstances, 
points 1  to 8 above should be checked before running the system for  the purpose of charging refrigerant and the 
outdoor unit liquid, gas and oil balance valves should be opened. 
 
During commissioning, it is important that you: 
  Keep a supply of R410A refrigerant at hand. 
  Keep the system layout, system piping and control wiring diagrams at hand. 
 
11.4 Commissioning Trial Runs 
11.4.1 Commissioning test run of single refrigerant system 
Once all the pre-commissioning checks in Part 3, 11.3 “Pre-commissioning Checks” have been completed, a test run should 
be performed as described below and a VC Pro Series System Commissioning Report (see Part 3, 12 “Appendix to Part 3 – 
System  Commissioning  Report”)  should  be  completed  as  a  record  of  the  operating  status  of  the  system  during 
commissioning. 
 
Note: When running the system for commissioning test runs, if the combination ratio is 100% or less, run all the indoor units 
and if the combination ratio is more than 100%, run indoor units with total capacity equal to the total capacity of the outdoor 
units. 
 
The test run procedure is as follows: 
1.  Open the outdoor unit liquid and gas stop valves. 
2.  Turn on the power to the outdoor units.   
3.  If manual addressing is being used, set the addresses of each indoor unit. 
4.  Leave the power on for a minimum of 12 hours prior to running the system to ensure that the crankcase heaters have 
heated the compressor oil sufficiently. 
5.  Run the system: 
a)  Run the system in cooling mode with the following settings: temperature 17°C ; fan speed high.   
b)  After one hour, complete Sheet A of the system commissioning report then check the system parameters using 
the UP/DOWN button on each outdoor unit’s main PCB and complete the cooling mode columns of one Sheet D 
and one Sheet E of the system commissioning report for each outdoor unit. 
6.  Finally, complete Sheet B of the system commissioning report. 
 
11.4.2 Commissioning test run of multiple refrigerant systems 
Once  the  commissioning  test  run  of  each  refrigerant  system  has  been  satisfactorily  completed  as  per  Part  3,  11.4.1 
“Commissioning test run of single refrigerant system”, run the multiple systems that make up a project simultaneously and 
check for any abnormalities. 
 
12 Appendix to Part 3 – System Commissioning Report 
A total of up to 11 report sheets should be completed for each system: 
  One Sheet A, one Sheet B   
  One Sheet D and one Sheet E per outdoor unit.