EasyManua.ls Logo

MTS Systems Exceed 40 Series - Page 42

Default Icon
44 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
The frame may overturn suddenly when lifting the frame.
An overturned frame can cause injury or death to anyone in the immediate
area.
Ensure that all persons in the immediate area are standing away from the
frame during lifting. Do not lift the frame more than 8 cm (3 in) off the floor.
Righting a Load Frame with a Crane
3. Slowly lift the frame until it is in an upright position and is lifted off the
floor.
4. Slowly move the load frame away from the shipping skid and remaining
packaging materials.
5. When the frame is clear of the packaging material, slowly lower the load
frame to the floor so that it is standing on four wedge iron in an upright
position.
6. Remove the slings from the top plate.
The frame can now be positioned into its operating location and then installed by
an MTS service representative. To position the frame into its operating location,
use the crosshead method to lift the frame. Refer to “Crosshead method” on page
38 for details.
WARNING

Other manuals for MTS Systems Exceed 40 Series

Related product manuals