MAIN INSTALLATION WARNINGS
1. The installation, maintenance and use of the appliance must be carried out by qualified
personnel able to safely perform the requested operations.
Carefully read this manual before performing any operations and follow all its indications.
2. Install the appliance as close as possible to the ambient where steam is to be distributed;
position with minimum steam tube distance, it is advised not to exceed 5 meters.
3. Install the appliance at a height enabling easy access to the control unit for parameters
adjustment and display viewing. A height of about 1 metre from the ground is advised.
4. Install the appliance at a height enabling easy access to inside the humidifier for the
replacement of the cylinder.
5. During functioning, certain humidifier parts, can exceed 60°C. Ensure the surfaces in contact
with it, are compatible with such values.
6. Do not install and use the humidifier near products or objects that can damage in contact with
water or humidity produced.
7. Avoid housing power supply cables in the same ducts with signal cables (probes and digital
inputs).
8. Reduce the lengths of the connection cables as much as possible, avoiding the wiring
assuming the spiral shape, damaging for possible inductive effects on the electronics.
9. Envision a general protection magnetothermic switch upstream of the humidifier.
10. All conductors used in the wiring, must be proportioned to support the load they must power.
11. If necessary to extend the probe, use suitably sectioned conductors and, however, not below 1
mm
2
.
12. Connect the water drain with a pipe having minimum 40 mm diameter, that does not generate
throttles, that it does not exceed the level of the spout in height, in any point.
13. For water charging, use only potable water with a pressure between 1 and 10 bar.
14. Before starting the humidifier, check default setting on the selected functioning mode
indicated in the attached CHECK LIST test sheet; should default setting be different to own