Refrigerant pipe installation
Performing air tightening test
Use tools for R410A only to prevent the inow of foreign substances and to resist the internal pressure.
Use dry Nitrogen gas to do an airtight test as below.
Apply pressure to the liquid side pipe, gas
side pipe with Nitrogen gas of 4.1 MPa (gauge
pressure), 595 psig.
If you apply pressure more than 4.1 MPa (gauge pressure), 595 psig.,
the pipes may be damaged. Apply pressure using pressure regulator.
Continue to apply pressure for minimum
24hours to check if the pressure drops.
After applying Nitrogen gas, check the change of pressure using
pressure regulator.
If the pressure drops, check if there is a gas leak.
If the pressure is changed, apply soapy water to check the leak.
Check the pressure of the gas again.
Maintain 1.0 MPa (gauge pressure), 145 psig of
the pressure before performing vacuum drying
and check for further gas leak.
After checking first gas leak, maintain 1.0 MPa (gauge pressure),
145psig to check for further gas leaks.
Nitrogen gas
If the joint of high pressure side is disconnected and the nitrogen gas come into contact with human body, injury
may occur. Tighten the joint connectionrmly to prevent dangerous situation.
CAUTION
AM0@@FXMDCH_IM_EN_03408A(1).indd 24 2013-03-04 오후 4:28:21