Instruction Sheet 716-504
S&C Series 2000 Circuit-Switchers
Outdoor Transmission
Model 2020 — With Vertical Interrupters
and Side-Break Power-Operated Disconnect
69 kV through 138 kV
Installation And Operation
Table of Contents
Section Page Section Page
Introduction
Qualified Persons ..............................2
Read this Instruction Sheet
.......................2
Retain this Instruction Sheet
......................2
Proper Application
..............................2
Usual Operating Conditions
......................2
Special Warranty Provisions
......................3
Warranty Qualifications
..........................3
Safety Information
Understanding Safety-Alert Messages ..............4
Following Safety Instructions
.....................4
Replacement Instructions and Labels
...............4
Location of Safety and Instruction Labels and Tags
5
Safety Precautions .......................... . 7
Shipping and Handling
Inspection ....................................8
Packing
......................................8
Storage
......................................9
Installation
Before Starting ...............................11
Installing the Mounting Pedestals and
High-Speed Base
...........................11
Installing the Operator
.........................14
Installing the Disconnect Pole-Units
...............16
Installing the Interrupters
.......................18
Installation—Continued
Connecting the Operator and Pole-Units to the
High-Speed Power Train
.....................21
Connecting Conductors
........................27
Remove the Interrupter Containers
................27
Setting up the Operator and Checkout
.............28
Adjusting Auxiliary-Switch Contacts
...............33
Operation
Understanding Trip-Free Operation ................34
Electrical Operation
...........................34
Manual Operation
.............................35
Decoupling
..................................36
Understanding the Gas-Pressure Indicator and
Safety Relief Device
.........................37
Understanding the Optional Remote
Gas-Density Monitor
........................37
Inspection Recommendations
...................37
Question and Answer IconNeed help?

Do you have a question about the S&C 2020 and is the answer not in the manual?

S&C 2020 Specifications

General IconGeneral
BrandS&C
Model2020
CategorySwitch
LanguageEnglish

Summary

Safety Information

Shipping and Handling

Interrupter Pressurization Hazard

Warns that interrupters are pressurized and should not be disassembled.

Installation

Operator Installation

Provides steps for physically installing the operator unit.

Interrupter Installation

Provides steps for installing the interrupter units into their positions.

Drive Linkage and Control Connections

Guides connecting operator and pole-units via the power train linkage.

Conductor and Container Removal

Details connecting conductors and removing interrupter containers.

Operator Setup and Final Checkout

Outlines procedures for operator setup, wiring, and final checks.

Final Assembly and Operation Initiation

Covers replacing covers, inserting fuses, and initiating operation.

Operation

Understanding Trip-Free Operation

Explains the instantaneous trip-free capability of the stored-energy mechanism.

Electrical Operation

Describes how to operate the circuit-switcher electrically (open/close).

Manual Operation

Decoupling and Related Operations