Air-Bag Operation Confirmation Procedure
RECLINIG "DOWN" and LEG "DOWN" buttons
POWER switch "ON"
(Simultaneously press)
ON/OFF button
1
3
2
5
6
7
8
4
Turn ON the POWER switch at the rear of the main body while simultaneously pressing the
RECLINING "DOWN" and LEG "DOWN" buttons on the control.
(This operation should be started with the POWER switch turned OFF).
When the examination mode is started up, both a back rest and a foot rest move slightly and
come to a stop.
1, Start-up of Examination Mode
Press the "ON/OFF" button on the control.
Check if the air-bag inflates sequentially as shown below.
* If there are any problems, check air leakage, breakage of air hoses, and the air-bags.
To remove the examination mode, turn OFF the POWER switch.
2, Air-Bag Operation Confirmation
1, Back rest, center
2, Back rest, right
3, Back rest, left
4, Back rest, upper
5, Back rest, lower
6, Seat, rear
7, Seat, front